Federal audit finds "a lot of work remains" in Puerto Rico's hurricane and earthquake recovery

FILE - A bridge is damaged after Hurricane Fiona hit Villa Esperanza in Salinas, Puerto Rico, Sept. 21, 2022. Puerto Rico continues reconstruction work after two devastating hurricanes and a string of strong earthquakes, spending less than 10% of the more than $23 billion available in federal funds, according to a U.S. government report released on Tuesday, Feb. 13, 2024. (AP Photo/Alejandro Granadillo, File)

SAN JUAN, Puerto Rico (AP) 鈥 Puerto Rico is trudging through reconstruction work after two devastating hurricanes and a string of strong earthquakes, and has spent less than 10% of more than $23 billion in available federal funds, according to a U.S. government report released Tuesday.

The U.S. territory has 鈥渁 substantial amount鈥 of permanent projects still pending as their costs soar and threaten to halt the rebuilding work, an audit by the U.S. Government Accountability Office found.

鈥淢ore than six years after hurricanes and , Puerto Rico鈥檚 recovery is ongoing,鈥 the report stated.

The GAO report also referred to a series of earthquakes that hit the island鈥檚 southern region in December 2019 and January 2020, causing millions of dollars in damage.

The report found that more than $11 billion of the $23.4 billion awarded by the U.S. Federal Emergency Management Agency following the hurricanes and earthquakes still requires the agency鈥檚 approval before Puerto Rico鈥檚 government can spend it.

It was not clear why the territory鈥檚 government has not yet taken the steps required to access the money. A spokesperson for Puerto Rico鈥檚 Office for Recovery, Reconstruction and Resiliency, which receives and awards federal grant funds, did not immediately return a message seeking comment.

However, documents show that Puerto Rico鈥檚 power company, Department of Education, and Aqueduct and Sewer Authority expect to submit applications to access the money by 2030 or later.

The federal funds are supposed to finance more than 9,300 permanent projects, with more than $13 billion slated for public utilities and $7 billion for public buildings and equipment.

However, rising costs have presented a challenge, according to the GAO audit that ran from November 2021 to February 2024.

The GAO noted that the cost of a water treatment plant exceeded its original estimate by more than 40%, while the cost of parts needed for a power plant rose from $9 million to $12 million.

The report said rising costs are of 鈥減articular concern鈥 because of their cumulative impact.

鈥淔or example, officials from Puerto Rico鈥檚 Aqueduct and Sewer Authority said they anticipate that they will only be able to complete about half of the agency鈥檚 planned projects,鈥 the report stated.

Contributing to the delays were interruptions in the global supply chain that increased the delivery time for construction materials needed by Puerto Rico鈥檚 power company from six months to up to three years, the audit found. Meanwhile, continue to plague the island.

Another challenge is a lack of workers ranging from architects to construction contractors, the report stated.

In an official response to the audit鈥檚 findings, Puerto Rico鈥檚 government requested more funding flexibility and noted that labor shortages in the local construction industry were a 鈥渟ignificant factor鈥 affecting recovery efforts.

The government also cited 鈥渟ignificant reductions鈥 in insurance coverage for several projects, as well as lengthy damage claim litigation between federal fund recipients and their private insurance companies.

鈥淭his limitation forces them to prioritize a select number of projects for development until insurance settlements are reached,鈥 the government's letter of response stated.

It also warned that when , the storm caused additional damage that could not be distinguished from the damage wrought by Hurricane Maria in September 2017 because 鈥渟everal subprojects have not yet been formulated.鈥

Other challenges include , with Puerto Rico recently emerging from the biggest U.S. municipal bankruptcy in history.

The GAO recommended that FEMA create a risk management plan, which it said the agency plans to do this month.

It also found that FEMA has successfully monitored Puerto Rico鈥檚 use of public funds via a review system, with the island improving its ability to manage such funds, at least from 2018 to 2020. Certain reviews of more recent years are pending.

The 好色tv Press. All rights reserved.