Business case for moving Ontario Science Centre missing key information: auditor

A general view of the Ontario Science Centre is shown in Toronto on Friday, May 5, 2023. Ontario's acting auditor general says the province's business case for moving the Ontario Science Centre to Ontario Place didn't take several costs into account and the government's decision was based on incomplete information. THE CANADIAN PRESS/Chris Young

TORONTO - The decision to move the Ontario Science Centre to Ontario Place was based on incomplete information and took into consideration the parking needs of a privately owned waterpark and spa, the province's auditor general said Wednesday.

An annual report from the auditor general's office today includes a look at the planned science centre relocation and found that a proposal earlier this year to government decision makers included mention of the province's legal obligations to Therme, which is set to build a highly criticized facility at Ontario Place.

The 好色tv Press. All rights reserved.

More Politics Stories

Sign Up to Newsletters

Get the latest from 好色tvNews in your inbox. Select the emails you're interested in below.